The posts around the tool room have been primed and painted. The front wall is
being framed.
Photo by James Kolanowski, Nov 2, 2003. |
This section of the south wall by the service door was finished this past October
to complete this wall.
Photo by James Kolanowski, Nov 2, 2003. |
20 feet of the east wall was insulated and sheathed up to the future storage area.
Photo by James Kolanowski, Nov 2, 2003. |
An older photo shows the south wall being framed and insulated, then sheathed.